Work in Progress
The following work is in progress (in no particular order)
- Trackwork – some changes in the yard, particularly:
- removal of "the hump"
- modifications to the wharf lines
- rewired trackwork leading to the engine shed.
- Ballasting – improvements to ballasting in the yard trackwork and behind the down platform.
- Uncoupling wagons in the yard – adjustments to the magnets that release the Spratt & Winkle couplings.
- Water Level – the “mean water level” has been agreed and work on associated embankments and tidal marshland underway.
- The Log Pond – the log pondbundaries have been set, and the bank type decided.
- Main lines – scenic work added behind the main running lines.
- Control System – wiring and power supplies are being completed.
- Buildings – the machinery in the creosote plant is completed, the timber drying shed location has been fixed but construction not started.
Still plenty to get stuck in to before October!
Running Evening
Members have spent some time “driving” trains on the mainlines and yard tracks.
EM gauge matters
Testing continues of all the rolling stock on Mawgan Porth.
The steam rail-motor has received a few minor repairs and is now running
0 Gauge matters
We are now in a period of running sessions. DCC will be used from time to time, 7mm members being advised in advance of those days.
Other Business
I hope to see as many as possible at the dinner, plus of course your other halves
Annual Dinner – Saturday February 24th 2018 at Potters Heron